Europe’s Rail Joint Undertaking (EU-Rail) aims to deliver, via an integrated system approach, a high-capacity, flexible, multimodal, sustainable, reliable and integrated EU railway network for European passengers and cargo.
To successfully address the expected outcomes, the Flagship Project stemming from this innovation action topic should research, develop, and deliver all the following capabilities and/or any other relevant capability within the following workstreams:
Workstream 1: DAC Interface A derailment and propelling safety tests, crash tests, climate chamber tests and initial tests to prove interchangeability of DAC coupler head/shank and draft gear across DAC solutions.
Workstream 2: Mix and match tests – initial tests to prove interchangeability of DAC interface A coupler head/shank and draft gear across DAC suppliers.
Workstream 3: Hybrid coupler for mainline and shunting locomotives, technical analysis and development of fitting solutions.
Workstream 4: Wagon Onboard Unit (WoBu).
Workstream 1: DAC Interface A derailment and propelling safety tests, crash tests, climate chamber tests and initial tests to prove interchangeability of DAC coupler head/shank and draft gear across DAC solutions.
The Flagship Project work should contribute to specifically provide:
In relation to the above, the action to be funded under this topic is expected to provide:
Derailment and propelling safety (TRL 6):
Crash tests considering (TRL 6/7):
Climate Chamber Tests (TRL 6/7):
Workstream 2: Mix and match tests – initial tests to prove interchangeability of DAC interface A coupler head/shank and draft gear across DAC suppliers.
The R&I work should provide the first results for interchangeable DAC interface A couplers for the handling, the transmission of forces and the behaviour for defined operational test cases.
Based on the test results, a comprehensive test specification should be defined for a fully developed mix and match test aiming for the interchangeability of interface A in DAC couplers.
The action to be funded under this topic is expected to:
Workstream 3: Hybrid coupler for mainline and shunting locomotives, technical analysis and development of fitting solutions.
The Flagship Project stemming from this innovation action topic should first identify the most suitable locomotive types (mainline and shunter locomotives) for the technical integration of power supply and communication systems.
The action to be funded under this topic is expected to deliver:
Workstream 4: Wagon Onboard Unit (WoBu).
The activities within this workstream should contribute to:
Different suppliers will have to be involved and to deliver the needed number of WoU. The wagon onboard unit prototypes can be provided by different companies if compliance to the requirements is reached. These units should be conceived according to the applicable Full Digital Freight Train requirements of FP5-TRANS4M-R, which would be made available to the Project stemming out of this call by the time of its start, and should already have demonstrated an adequate level of interoperability on the reference test system in a relevant environment. The project should perform demonstrations in operational environments (TRL 7). It must be foreseen that the number of WoUs provided and supporting the EDDP train functions would amount to minimum thirty (30) units. These units should be conceived according to the applicable Full Digital Freight Train requirements.
The funding rate of the action is 60% of the eligible costs to achieve the leverage effect established in the SBA.
Each Consortia may decide internally different funding rates in line with the provisions of Article 34 of Horizon Europe nevertheless complying with the overall funding rate of 60%.
The granting authority can fund a maximum of one project.
Applicants should ensure that their proposals and consortium reflect the aggregated expertise to perform the activities and achieve the objectives set by the topic.
The applicants are expected to gather the necessary technical expertise from Operators, Infrastructure Managers, DAC Suppliers, Loco Suppliers, Loco Keepers as well as the capabilities, capacity and proven experience to execute the required test program and to provide the test results. The applicants should also ensure the provision of the required test infrastructure and test assets and the managerial expertise for its execution. Applicants must ensure their capacity to industrialise and respect the normative landscape applicable to electronic / electropneumatic / electromechanical products for passenger and/or freight railway applications.
Complementary expertise from research institutes and academia, could allow:
Complementary expertise from other sectors and parties, with particular attention to SMEs and Start-ups, which may contribute to enhance the actions’ outcome.